Description
A community swimming pool is coming to City Park, located at 251 CR 200. The pool is expected to open towards the end of the 2022 swimming season.
Project Status
Bid awarded to STR Constructors for the Swim Center and Patriot Underground, LLC for the lift station & force main.
Funding
Texas Parks & Wildlife Grant - $500,000
City Contribution - $1,300,000
Total Project Cost - $1,800,000
Expected Construction Timeline
October 1, 2021 to July 31, 2022
Expected Completion Date
August 2022